Wednesday, September 20, 2017

Building A Pond...

4:50 pm - 47 degrees - foggy, raining...

When we were driving around looking for property 12 years ago, we came upon this near-perfect rural off-grid property... and we were sold!

Our property has a good amount of acreage, gorgeous views, a nice home site, and it’s a nice distance to and from civilization.  It was perfect... except for one small thing – it was missing a visible water feature.  Yes, a river bisects our lot, but we can’t see it from the house.

I have always wanted to live on a lake or have a large pond or some kind of water feature within sight of the house.  It's only taken 12 years, but we finally have a visible water feature – a pond!

A pond offers numerous benefits for landowners: entertainment for the family, water for wildlife, aquaculture, fire protection, erosion control, and aesthetics are but a few. 

And in our case, the pond will also hopefully offer another source of power – hydroelectric power. 

For those of you who don’t know what hydroelectric (or hydropower or hydroenergy) is – it’s a reliable source of renewable energy that runs 24/7 for very little cost.  Power is generated from the movement of water, like waterfalls or streams, water that is stored in dams, as well as flowing in river to create electricity.  The water flows through a turbine to help generate electricity; using the energy of falling or flowing water to turn the blades.  The rotating blades spin a generator that converts the mechanical energy of the spinning turbine into electrical energy that we can use to power our home.

Even though a pond has so much to offer, there are a lot of factors that needed to be considered first.  Factors like:
 - Is the land and soil actually suited for a pond?
 - Can we build the pond ourselves?
 - What size of pond do we want and what size will fit?
 - How much will this project cost?
 - How long will this project take?

While Tony is the researcher, thinker, and planner, I am one to jump in with both feet now.  So when he told me that he was thinking that he could put in a pond and wanted to know what I thought – my response was YES, the bigger the better!


After walking around the designated area he had picked out and visualizing his plan of attack, Tony started digging, and digging, and digging.





The underground springs Tony tapped into, quickly started filling the hole and eventually the big hole started to look like a pond.  Before the pond got too full, he added a 4” pipe that is about 2’ below the water line for our future hydropower source.  




Tony also added an 18” culvert for an overflow.


After getting the edges, top and surrounding area cleaned up, we spread grass seed covered with Turf Mulch.  The Turf Mulch is a naturally organic product that is a ground dressing for the newly seeded area.  It will help the ground retain moisture, form a protective mat over the seed, help the grass seed germinate quicker and help with erosion control until the grass grows in.


And we now have a 10' deep by 40'x50' trout pond!  The water level is currently at the uncapped hydro pipe, which he painted black so it would blend in a little more.  Tony wanted to keep the water at the lower level until the grass starts to grow.  The trout will be coming in about a month or so.  So excited for this project and how it is turning out!  My husband is amazing!!

Thursday, January 5, 2012

Gravity Fed Water System {Water Storage}…

37 degrees - 9:14 am - foggy... 

All the trenching for our gravity fed water system is finally done, now onto the cold-water storage tank.



We are using a used food grade IBC Tote (which has been cleaned out several times) that we got off of Craigslist.


Tony has placed the water tank at the end of the trench and plumbed it with an intake line, vent pipe, and a p-trap.
 


The tank is surrounded on all sides with plywood to keep the dirt from crushing the tank.  All water lines and tank will be completely buried; the only thing you will see will be the top two feet of the vent pipe, which will be spray-painted brown.


The only thing left to do is lay out the intake line, which will be above ground, to the water source.

To be continued…

Monday, December 26, 2011

Gravity Fed Water System {Still Trenching}…

35 degrees - 6:33 pm - cloudy...

Our last post about trenching the gravity fed water system was over a month and a half ago.  Since then, we have been busy with work, holidays, and other projects around the house. 

Now that the main winter holidays are behind us, and there is no snow on the ground, back to trenching he goes.  Tony now has just over 1,500 feet of pipe laid, and still has about another 150 feet to go to the holding tanks.  Once he gets to the holding tank area then he will have to lay another 200 feet of pipe from the new well down to the holding tanks.

The last few hundred feet of trenching has not been easy since Tony has had to dig through large amounts of rock.  The final stretch will hopefully be much easier and go much quicker.

Here are some pictures of what Tony has done so far…


laying out the pipe over the open trench, getting ready to put it in

last section of trench has the pipe in and is covered up -
ready to start trenching the last stretch 

the mini bosses out giving their opinions on what they think needs to be done

Jack pointing out the pipe to me and explaining what Daddy is trying to do

To be continued…

Wednesday, December 7, 2011

Propane…

32 degrees - 2:25 - foggy...

This afternoon one of our two 500 gallon propane tanks was delivered.  Tony had previous cut out and cleared an area for the propane tanks to sit that is 200 feet away from the house and cannot be seen.  If we have to have propane tanks, I don’t want to see them!  The area is big enough to fit four 500-gallon tanks, but hopefully we won’t need that much.  Tony also had all the conduit lines ran and buried between the house and the propane tank area.  So when the propane guys got here they just had to unload the tank from their truck…


…then Tony jumped into the excavator and placed the tank…



…then the kids had to check it out…


…then one of the propane guys and Tony (down in the hole)
had to push the propane line thru the 200 feet of conduit…


…so it popped out in this hole by the house (the last 6 feet where the
hardest, having to push thru the last of three 45 degree bends)…


…after the conduit was pushed thru then it was time to hook up the regulator…


…then fill the tank (looking out the back window) and
after $1067 worth of propane we are done!


Saturday, November 12, 2011

Gravity Fed Water System {Trenching}…

35 degrees - 9:28 am - foggy...

The past several days Tony has been working on digging a trench and laying the pipe for the gravity fed water system.  Our well requires a pump, which uses a lot of electricity, while the gravity fed system only requires elevation.  We will still have our well and pump available if needed, but prefer the simplicity of gravity.

So far, Tony has laid just over 1,000 feet of pipe, and still has about another 500 feet to go.  Here are some pictures of what he has done so far…

Isolation Valves

pulling back all the limbs and brush to make the smallest opening possible

Valve Cover for the Isolation Valves

using tie downs to hold back the limbs so the excavator can get thru

the muscle

trench has been dug, water lines have been laid, everything has been covered up
and put back - by next summer this little trail wont even be noticed

final stretch of the trench running up and along the runway (aka main driveway)

To Be Continued…

Monday, October 3, 2011

Weekend Projects…

50 degrees - 10:17 am - raining...

It’s a cold, rainy, fall day outside but thankfully it’s nice, warm and cozy inside because the weather forecast for this week is showing nothing but cold temps and more rain.  Fall is definitely here, and the number of nice days is now limited.

Tony spent the entire weekend out in the mud and rain trying to get some important projects done – smoothing out the backyard and getting the conduit project completed. 

After spreading out the large dirt pile in the backyard, we were left with a yard full of rocks and sticks.  So Tony borrowed our neighbors John Deere tractor to remove the debris and smooth out the dirt.  Now all we need to do is plant grass seed, hopefully it’s not too late in the season for that.

the backyard doesn't look that big --- but then I remember
that those stars are 12'x12' and the backyard is the size of the lot
that our last 2,164 sq ft house sat on --- so yes, it's pretty big in comparison.

He was also able to finally dig the last stretch of the trench for the conduit lines, from the edge of the backyard over to the well and propane tank area.  The conduit lines have been laid out but we were two sticks short.  Once we get those last two sticks in, the trench can be filled in. 

conduit lines at the edge of the backyard


conduit lines - black line turning left heading to the well and the gray lines
heading staight to the propane tank and generator house area

conduit lines for the propane tanks and generator


looking back towards the house and backyard

I just love it when things get to be crossed off the To-Do-List!

Sunday, September 25, 2011

Laying Conduit Project...

51 degrees - 10:53 am - overcast and lightly raining...

Nothing is ever simple or easy here on the mountain.  What I though would take maybe a weekend or two, to get the entire conduit laid out from the house up to the well, propane tanks and generator house area, has instead been going on since April.  Of course the obvious challenge has been the weather.  This summer has been a ‘blink and you miss it’ kind of summer; the worst summer up here on the mountain that anyone can remember. 

The next challenge has been trying to get the groundwork, clearing and leveling, completed so the final stretch of the conduit trench can be dug.  This is also the area that we were looking at putting our garden.  But after this summer we are going back to the drawing board on the garden ideas and plans.  But I wont get into that right now, that will have to be another post.

It is currently raining outside so no work will be getting done on this project today.  All we need is a few more nice days and we can check this project off our to-do-list!

Here are a few pictures of the progress since April…

April 9, 2011 - majority of the snow is gone, we can start clearing the area



April 14 - time to do a little pruning

conduit lines end at the edge of the yard, waiting for the final strech
up to the well, propane tanks and generator house




Sep 24 - moving all the extra dirt over to the edge of the property line
to make a 20 foot high privacy berm


Sep 25 (this morning) - ground work is almost done!